Opens in a new tab

Adhering to Obligations in Payment Schedules

Written by Priyanka Ram

Written by Priyanka Ram

2 min read
Published: March 27, 2023
Legal Topics
Building & Construction Law
Page Content
Page Content

The recent Queensland Court of Appeal decision of Allencon Pty Ltd v Palmgrove Holdings Pty Ltd trading as Carruthers Contracting [2023] QCA 6, highlights for all parties to carefully consider their obligations when issuing a payment schedule within the stipulated time period. Failure to do so would result in judgment in the full amount of a payment claim.

In this case, Allencon Pty Ltd (Allencon) entered into a subcontract with Palmgrove Holdings Pty Ltd trading as Carruthers Contracting (Palmgrove) in 2021 to carry out certain construction roadworks as part for the lump sum of $2.08 million (Subcontract).

Allencon submitted a payment claim in an amount of $955,079.48 on 24 December 2021 (Payment Claim).

In Queensland, section 76 of Building Industry Fairness (Security of Payment) Act 2017 (Qld) (Act) provides parties who do not intend to pay the full claimed amount by the due date, must give the claimant a payment schedule by the earlier of:

  1. 15 business days after receipt of payment claim; and
  2. the time stated under the contract.

Further, the conditions of the Subcontract included a term to the effect that payment schedules were required to be given by Palmgrove within 21 calendar days of receipt of the claim.

In the present case, 21 calendar days were less than 15 business days under the contract because under the Act a business day excluded weekends, public holidays, and the days from 22 December to 10 January.

On 28 January 2022, Palmgrove issued a payment schedule, which was within the 15 business days of receiving the payment claim as defined by the Act, but not within 21 calendar days under the contract.

The Court of Appeal held that the payment schedule was not served within time, because it was not served within 21 days specified in the contract.

This case confirms that parties should carefully consider differences between the time for service of payment schedules provided for in a construction contract and the time for serve of payment schedules under the Act.

If you have any questions or concerns please contact our Building & Construction Director Michael Terry-Whitall on 02 6188 3600

Related articles

Building & Construction Law

Obtaining Summary Judgement

Obtaining summary judgment under the Building and Construction Industry Security of Payment Act 1999 (NSW) (SOPA) When a payment claim...

Read more about Obtaining Summary Judgement

Building & Construction Law

Case Note: Equa Building Services Pty Ltd v A&H Floors 2 Doors Australia Pty Ltd [2022] NSWSC 152

In this case, the Supreme Court of New South Wales reinforced the importance of following the proper methods of service...

Read more about Case Note: Equa Building Services Pty Ltd v A&H Floors 2 Doors Australia Pty Ltd [2022] NSWSC 152

Building & Construction Law

Construction Case Summary: Bailey, in the matter of Megacrane Holdings Pty Ltd (administrator appointed) [2022] FCA 733

On 15 June 2022 the Court ordered, pursuant to Section 447A(1) of the Corporations Act 2001 (Cth) (the Act), that...

Read more about Construction Case Summary: Bailey, in the matter of Megacrane Holdings Pty Ltd (administrator appointed) [2022] FCA 733
Two silhouetted construction workers standing on scaffolding at a building site during sunset, with a dramatic orange-to-blue sky and metal framework creating a striking industrial scene

Building & Construction Law

Chamberlains Secures Major Win: Court Rules Contractual “Deeming Clause” Void, Upholds Security of Payment Act

Chamberlains Law Firm has secured a significant victory for its client, Sharvain Facades Pty Ltd (Administrators Appointed), in a crucial...

Read more about Chamberlains Secures Major Win: Court Rules Contractual “Deeming Clause” Void, Upholds Security of Payment Act