The Supreme Court of Western Australia has delivered one of the few decisions to shed light on when provisions contained in Schedule 1 to the Construction Contracts Act 2004 (WA) (CCA) will be implied into a construction contract.
Unlike the East Coast security of payment regimes, statutory provisions under the CCA regulating matters such as:
only apply if the construction contract is silent on those matters.
Where silence exists, the relevant terms contained in the corresponding Division of Schedule 1 are implied.
Background: Total Eden Pty Ltd v Charteris [2018] WASC 80
In Total Eden Pty Ltd v Charteris [2018] WASC 80, the WA Supreme Court clarified the limits of when Schedule 1 terms are implied.
Key facts
Adjudicator’s approach
The adjudicator implied the entire Division 5 into the contract, resulting in new, statutory payment timing obligations that conflicted with the parties’ written agreement.
The Supreme Court’s Findings
The WA Supreme Court held that the adjudicator erred, quashed the entire determination, and confirmed the following principles:
The CCA does not permit the wholesale implication of a full Division of Schedule 1.
Instead, the Court held that:
Implying all of Division 5 created an internal inconsistency with the contract’s existing payment terms.
Clause 7(3) of Division 5 could not be implied because:
The Court concluded the adjudicator incorrectly implied clause 7(3), and therefore made a jurisdictional error, invalidating the whole determination.
Practical Implications for WA Contracting Parties
Contracting parties should ensure that their construction contracts:
Key Takeaways
We’re Here to Help
We at Chamberlains understand the emotional and financial stress that come with litigation. Should you require further information about how costs can be recoverable in matters before the Federal Court and Federal Circuit Court, please do not hesitate to contact our office for a consultation with our construction law team.